|
W.Va. Towboat Photos |
|
Barges on dam at Belleville Lock Home | Loss of the Belleville Pool Friday, January 7, 2005- On the morning of January 6th, the M/V Jon J. Strong encountered problems while shoving northbound out of Belleville Lock and Dam at mile marker 204. The vessel had 12 total barges in tow when the lead barges encountered the strong currents, breaking couplings and sending 9 of the 12 barges down on the dam. Some of the floating barges were pulled off and down through the dam, but a total of four did sink above the dam. These photos were taken from the upper parking lot at the Lock and Dam on the Ohio side.
Friday, January 14, 2005- The river at Parkersburg crested on January 8th at the level of 42.8 feet, almost 7 feet above flood stage. The river was falling very fast, but another storm dumped more rain over the region bringing the river back up to just within flood stage. The swift water conditions at the dam hindered salvage efforts, and most equipment was shifted into the small chamber to await more favorable conditions. These photos were also taken from the Ohio side in the upper parking lot and the lower fishing parking lot.
Friday, January 21, 2005- After the floodwaters receded, another problem came to light, the loss of navigational pool between Belleville and Willow Island Locks. The industry prepared as much as it could with as little notice as they had. The river was falling at a moderate rate, forcing the removal of all red flag barges from the pool by 1700 on January 17th. The levels at Belleville lock reached the critical stage of 6 feet on the upper gage at 0200 on January 19th, and no vessels were allowed to transit the pool after that point. Some projections indicated pool to drop to the levels of the old lock systems, or around 10 feet below normal pool in places. Furthermore, salvage operations were proceeding very slowly, being hampered by frigid temperatures and a winter storm system, which covered the area with a 4" blanket of snow. The following photos were taken from the W.Va. side above the hydro plant and at the fishing parking lot. River Levels:
Friday, January 28, 2005- Progress was very slow in the beginning, but salvage progressed as the week went along. Two barges were removed from the dam, leaving two remaining. The removed barges were pulled down below the dam, and placed along the left descending shore. They were pulled from that location at a later time. Although these photos just show one barge left, there is actually another barge that is still sunk under gate # 3. The following photos were taken from the W.Va. side above the hydro plant and at the fishing parking lot. River Levels:
As of January 31st, all gates were cleared at 1455. The AEP 611B was not blocking any gates, and the decision was made to raise the barge at a later date. The gates were tested, and the pool began to raise at 1800. As of that time 47 vessels were waiting for the pool to reopen. The river level rose quickly and was back at normal pool in just over 12 hours. The pool was reopened at 0600 on February 1st, and priority vessels were allowed to enter at that time.
Friday, June 17, 2005- A few days earlier in the month of June, River Salvage started work again at Belleville to raise the AEP 611B and also raise a few barge sections that were left below the dam in January. Work progressed rather quickly, due to the very favorable weather and water conditions. When I arrived at Belleville on this day, much of the salvage work had already been completed.
All images © C.R. Neale |